Skip to main content
U.S. flag

An official website of the United States government

Moving Mountains: Elwha River Still Changing Five Years After World’s Largest Dam-Removal Project: More than 20 million tons of sediment flushed to the sea

September 5, 2018

Starting in 2011, the National Park Service removed two obsolete dams from the Elwha River in Olympic National Park, Washington. It was the world’s largest dam-removal project. Over the next five years, water carrying newly freed rocks, sand, silt and old tree trunks reshaped more than 13 miles of river and built a larger delta into the Pacific Ocean.

animated satellite images showing sediment outflow over time from Elwha River
Computer animation showing changes at the mouth of the Elwha River from 2011 through 2016. Brown-shaded areas are elevations above low tide; blue shades indicate seafloor depths below low tide. Watch the animation loop to see the mouth of the Elwha River grow and change as millions of tons of sediment moved downstream from Olympic National Park to the Pacific Ocean. (Public domain.)

Scientists from the U.S. Geological Survey and six research partners recently published a paper summarizing a half-decade of changes to the shape and sediment of the Elwha River after dam removal.

Map of part of Olympic Peninsula, Washington, showing mouth of Elwha River
Map showing the location of the Elwha River in the state of Washington, including the sites of two dams and their reservoirs, since removed. (Public domain.)
diagram of Elwha river sediment erosion and deposition
Diagram of Elwha River sediment changes five years after dam removal began. Mt = millions of metric tons (1,000 kilograms or 1.1 US tons). (Public domain.)

 

Of the 33 million tons of sediment trapped behind the dams, about 8 million tons resettled along the river or at the mouth, and another 14 million dispersed into the ocean. It would take more than 70 dump trucks running 24 hours a day for five years to move that much dirt and debris downstream. Piled up, the sediment would form a cone about one-third of a mile in diameter and taller than a 50-story building.

Illustration comparing amount of sediment with 50-story building
Illustration comparing a hypothetical conical pile of Elwha River dam sediment washed downstream to the Statue of Liberty and a 50-story building. (Public domain.)

 

“It really emphasizes the power of water to move mountains,” said USGS geomorphologist Andy Ritchie, lead author on the peer-reviewed article in the journal Scientific Reports. “Five years later, the Elwha was more like an undammed river than a river choked with sediment. Even without exceptional flows, a river can recover very rapidly after removing a dam or two.”

Glines Canyon Dam removal
Glines Canyon Dam on the Elwha River, during dam removal. (Credit: Jeff Duda, U.S. Geological Survey, public domain.)​​​​​​​

 

Ritchie said 90 percent of the sediment released by the project flowed downstream to the river delta and into the ocean. Even after the main pulse of sediment had passed two years after demolition started, the shoreline near the river’s mouth continued changing.

“I think it surprised everybody that the sediment moved out of the river as fast as it did,” said USGS research geologist and co-author Amy East. “We thought we'd be seeing major changes for 10 years or so. Instead, the peak disturbance only lasted about five months.” Yet the river continued to transform. A few years later there was a large flood on the Elwha; the river changed course in one area and heavily damaged a road and two campgrounds.

View from the sky looking inland at a river mouth that is flowing into open waters heavily laden with sediment in contrast.
Sediment from the Elwha River flows into the ocean after dam removal. (Credit: Jonathan Felis, U.S. Geological Survey, public domain.)​​​​​​​

Researchers measured changes in the shape of and location of sediment in the Elwha River and in the ocean offshore using a variety of techniques, including pre-dam survey records, GPS and 3D-lidar (laser pulse) surveys, air photos and river gages. Scientists from the USGS, the National Park Service, the U.S. Bureau of Reclamation, Washington Sea Grant, NOAA Fisheries, the University of Washington and the Lower Elwha Klallam Tribe worked together to collect, process and analyze mountains of river data.

4-photos of scientists doing field work on boats, and in or near the water
Researchers survey Elwha River elevation and depths. Clockwise from upper left: setting up a traditional survey instrument above the river; measuring river depths from a kayak with sonar and GPS; walking the beach with GPS backpacks; and determining offshore depths using a personal watercraft with GPS and sonar. (Public domain.)

“The Elwha project has been one of the greatest examples of collaboration that I’ve ever been a part of,” said Ritchie. “But there’s still a tremendous amount to learn from the river.”

The new paper, “Morphodynamic evolution following sediment release from the world’s largest dam removal,” is online. Other recent USGS-led publications on the impacts of Elwha dam removal include “Coastal habitat and biological community response to dam removal on the Elwha River,” and “Increased sediment load during a large-scale dam removal changes nearshore subtidal communities.” For more information on USGS Elwha River research, visit our website.

Get Our News

These items are in the RSS feed format (Really Simple Syndication) based on categories such as topics, locations, and more. You can install and RSS reader browser extension, software, or use a third-party service to receive immediate news updates depending on the feed that you have added. If you click the feed links below, they may look strange because they are simply XML code. An RSS reader can easily read this code and push out a notification to you when something new is posted to our site.

Was this page helpful?