Skip to main content
U.S. flag

An official website of the United States government

Level II scour analysis for Bridge 6 (ALBUTH00150006) on Town Highway 15, crossing Mud Creek, Alburg, Vermont

January 1, 1997

This report provides the results of a detailed Level II analysis of scour potential at structure
ALBUTH00150006 on Town Highway 15 crossing Mud Creek, Alburg, Vermont (figures
1–8). A Level II study is a basic engineering analysis of the site, including a quantitative
analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of
a Level I scour investigation also are included in Appendix E of this report. A Level I
investigation provides a qualitative geomorphic characterization of the study site.
Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT)
files, was compiled prior to conducting Level I and Level II analyses and is found in
Appendix D.
The site is in the Champlain section of the St. Lawrence Valley physiographic province in
northwestern Vermont. The 2.90-mi2
drainage area is in a predominantly rural and forested
basin. However, nearly a third of the drainage, including the location of the study site, is
wetland.
In the study area, Mud Creek has an sinuous channel through wetland with a slope of
approximately 0.0002 ft/ft, an average channel top width of 42 ft and an average bank
height of 2 ft. The channel bed material ranges from clay to sand with an estimated median
grain size (D50) of 0.047 mm (0.00015 ft). The geomorphic assessment at the time of the
Level I and Level II site visit on June 26, 1995, indicated that the reach was stable.
The Town Highway 15 crossing of Mud Creek is a 30-ft-long, one-lane bridge consisting of
one 28-foot steel-beam span (Vermont Agency of Transportation, written communication,
March 7, 1995). The opening length of the structure parallel to the bridge face is 26.7 ft.
The bridge is supported by vertical, concrete abutments with wingwalls. The channel is
skewed zero degrees to the opening and the opening-skew-to-roadway is also zero degrees.
Channel scour, approximately 2 ft deeper than the mean thalweg depth, was observed in the
middle of the channel extending from 5 to 35 ft upstream of the bridge. The only scour
countermeasure observed at this site was some small stone, possibly type-1 stone fill (less
than 12 inches diameter), partially covering the channel bed under the bridge. Additional
details describing conditions at the site are included in the Level II Summary and
Appendices D and E.
Scour depths and recommended rock rip-rap sizes were computed using the general
guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995).
Total scour at a highway crossing is comprised of three components: 1) long-term
streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction
in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and
abutments). Total scour is the sum of the three components. Equations are available to
compute depths for contraction and local scour and a summary of the results of these
computations follows.
Contraction scour for all modelled flows ranged from 6.2 to 7.2 ft. The worst-case
contraction scour occurred at the 500-year discharge. Abutment scour ranged from 2.0 to
2.4 ft and 2.1 to 2.6 ft on the left and right abutments respectively. The worst-case abutment
scour occurred at the 500-year discharge. Additional information on scour depths and
depths to armoring are included in the section titled “Scour Results”. Scoured-streambed
elevations, based on the calculated scour depths, are presented in tables 1 and 2. A crosssection of the scour computed at the bridge is presented in figure 8. Scour depths were
calculated assuming an infinite depth of erosive material and a homogeneous particle-size
distribution.
Usually, computed scour depths are evaluated in combination with other information
including (but not limited to) historical performance during flood events, the geomorphic
stability assessment, existing scour protection measures, and the results of the hydraulic
analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values
documented herein.

Publication Year 1997
Title Level II scour analysis for Bridge 6 (ALBUTH00150006) on Town Highway 15, crossing Mud Creek, Alburg, Vermont
DOI 10.3133/ofr97397
Authors Scott A. Olson
Publication Type Report
Publication Subtype USGS Numbered Series
Series Title Open-File Report
Series Number 97-397
Index ID ofr97397
Record Source USGS Publications Warehouse